We are moving right along on the construction. We now have irrigation on 4, 5, 6 and 7. It has been started on 3 as well. The main line should be completely looped around the course by Wednesday! Bunker construction started on Saturday along with some grassing. The last two greens on the course have been approved for drainage, gravel and mix. These will be completed this week. The Nicklaus architect will be back out for three days on the week of July 23 and will start floating greens. Once the greens have been floated, will will start seeding and growing them in. The plan is to start spigging tees, fairways and rough this week as well!
Here is the 1st bunker in the construction process. Sand should be finished today
New path on #7
Last week, we also started our tee and collar conversion. Collars should be finished by Wednesday and tees within the next two weeks.
Existing grass being stripped from 3 tee surround
Stay tuned for another update in the next week or so. Have a great week!